KABUL - KANDAHAR STATE HIGHWAY | GULSAN HOLDİNG

KABUL - KANDAHAR STATE HIGHWAY


The scope of the project was to design, reconstruct and rehabilitate the portion between 317 and 432+000 km of Kabul-Kandahar Road, which is a part of 3300 km of the National Highway Network that was greatly damaged due to troublesome years. It was planned to be reconstructed within a 5-year period. The work included 25 cm thickness of hotmix pavement, expanding the road, infrastructure, superstructure, culvert, structures, traffic signs and markings. The project was carried out by Gulsan-Cukurova Joint Venture.

Client : Louis Berger Group Inc.
Location : Kabul-Kandahar, Afghanistan
Construction Period : 2003-2004




       

PROJECT MAIN QUANTITIES

       
Earthworks Pavement Works Concrete Works Bridge Rehabilitation
1,680,000 cum 535,525 ton 5,500 cum 4,220 sqm
       