CONSTRUCTION OF VARIANT LEVELS OF INTERCHANGES, BRIDGES AND COLLECTOR ROADS ON SAMSUN-ÇARŞAMBA STATE HIGHWAY


The purpose of the Project was to ease the vehicular traffic density by replacing the grade crossings with flyover junctions.

The Project involved the construction of three flyover junctions and a water channel crossing bridge on different sections of the highway. Lenghts of the flyovers are; 183m, 183m, 817m with a total lenght of 1.183m. The elevated approaches to the flyovers are supported by reinforced earth walls. The works also included the construction of collector roads and sidetracks.

Employer: Directorate of Highways, 7th Region
Location: Samsun
Construction Period: 24 months


PROJECT MAIN QUANTITIES

       
Earthworks Concrete Works Reinforced Steel Bored Pile Works (Ø60, Ø100 & Ø120)
656.000 m³ 90.500 m³ 21.300 ton 71.000 m
       
Reinforced Earth Walls Plant Mix Base and Sub-base Bitumen Hot Mix Asphalt Stone Mastic Asphalt
116.000 ton 103.260 ton 12.920 ton 28.125 m²
       
Precast Beams      
19.200 m³      
       