KANDAHAR - HERAT STATE HIGHWAY PROJECT II


The scope of the project was to reconstruct the section between km 406+000 and km: 456+000 of the mostly deteriorated Kabul-Herat Motorway, which is a part of the vastly damaged 3,300 km National Highway Network. The project was carried out by Gülsan Cukurova Joint Venture.

Client : Louis Berger Group Inc.
Location : Herat, Afghanistan
Construction Period : 2004-2005




       

PROJECT MAIN QUANTITIES

       
Earthworks Pavement Works Concrete Works Rigid Pavement Rubbilizing
440,000 m³ 560,000 tons 2,350 m³ 365,000 m²
       
Bridge Rehabilitation
     
1,351 m²
     
       